粉料撒布車與冷再生拌和機的配套使用
來源:http://www.bystreet.cn/ 日期:2021-08-11
(1)測量放樣。
(1) Survey and setting out.
測設中樁,直線段每20m設一樁,平曲線段每10m設一樁,并在兩側路肩邊緣外設指示樁,見圖2。在指示樁上用明顯標記標出水泥土邊緣的虛鋪高度。
Survey and set middle stakes. One stake is set every 20m in straight line section and one stake every 10m in flat curve section, and indicator stakes are set outside the edges of shoulders on both sides, as shown in Figure 2. Mark the virtual paving height of cement soil edge with obvious marks on the indicator pile.
(2)土方攤鋪。
(2) Earthwork paving.
原地面、水泥攪拌樁、砂礫換填驗收合格后,恢復中樁和兩側邊樁,檢測基底高程,在基底上用石灰線畫出中線、邊線和布土方格(圖3)。根據實測虛鋪系數(shù)計算虛鋪厚度,壓實厚度按照20cm控制。根據運土車大小,計算布土方格尺寸。
After the original ground, cement mixing pile and gravel replacement are accepted, restore the middle pile and side piles on both sides, detect the elevation of the base, and draw the center line, side line and soil distribution grid on the base with lime line (Fig. 3). The virtual paving thickness is calculated according to the measured virtual paving coefficient, and the compaction thickness is controlled as 20cm. Calculate the size of soil distribution grid according to the size of soil truck.
(3)整平。
(3) Leveling.
推土機粗平后做出標高控制點,然后用平地機精平,整理出路拱和橫坡,見圖4。整平后要及時檢測素土的含水量,按比含水量高出2%控制。隨后檢測土的含水量是否均勻并符合要求,合格后進入下道工序。當含水量過低時,采用水車補水調整。當含水量大時,需翻開晾曬。
冷再生機租賃
Make elevation control points after rough leveling by bulldozer, and then fine level with grader to sort out outlet arch and cross slope, as shown in Figure 4. After leveling, the water content of plain soil shall be detected in time and controlled as 2% higher than the optimal water content. Then, check whether the water content of soil is uniform and meets the requirements, and enter the next process after it is qualified. When the water content is too low, the water truck shall be used for water replenishment adjustment. When the water content is large, open it for drying.
(4)撒布水泥。
(4) Spread cement.
采用粉料撒布車進行水泥撒布,見圖5。撒布前需要根據水泥劑量計算出每的水泥撒布量,然后只需駕駛員在車輛控制器中輸入每的水泥撒布量和撒布寬度即可。輸入后,車輛控制系統(tǒng)自動計算出相關參數(shù)并開始均勻撒布。
The powder spreader is used for cement distribution, as shown in Figure 5. Before spreading, the cement spreading amount per square meter needs to be calculated according to the cement dose, and then the driver only needs to input the cement spreading amount and spreading width per square meter in the vehicle controller. After input, the vehicle control system automatically calculates relevant parameters and starts uniform distribution.
(5)拌和。
(5) Mixing.
水泥撒布完成后采用冷再生拌和機拌和,見圖6。從兩側向中間方向進行拌和,拌和速度為1~3.3km/h,拌和次數(shù)不少于1次,直到翻拌均勻為止。翻拌過程中,應安排人隨時檢查翻拌深度是否滿足要求。翻拌完成后檢查含水量,如果含水量滿足要求,混合料色澤均勻一致,沒有灰條、灰團和花面,沒有粗細顆粒“窩或帶”就算拌和合格。同時采用EDTA滴定法快速測定水泥劑量。若水泥量不足,應補撒水泥,重新滴定直水泥劑量滿足大于等于4%的要求,然后重新拌和符合要求。
After the cement distribution is completed, the cold recycling mixer is used for mixing, as shown in Figure 6. The mixing shall be carried out from both sides to the middle. The mixing speed shall be 1 ~ 3.3km/h, and the mixing times shall not be less than once until the mixing is uniform. During the mixing process, a person shall be arranged to check whether the mixing depth meets the requirements at any time. Check the water content after mixing. If the water content meets the requirements, the color of the mixture is uniform, there is no ash strip, ash mass and flower surface, and there is no "nest or belt" of coarse and fine particles, the mixing is qualified. At the same time, EDTA titration method is used to quickly determine the cement dose. If the amount of cement is insufficient, the cement shall be added, titrated again until the cement dose meets the requirements of greater than or equal to 4%, and then remixed to meet the requirements.
拌和過程中,及時檢查混合料的含水量。含水量宜略大于含水量1~2個百分點。如果混合料的含水量不足,利用灑水車灑水潤濕。
During mixing, check the water content of the mixture in time. The water content should be slightly greater than the optimum water content by 1 ~ 2 percentage points. If the water content of the mixture is insufficient, use the sprinkler to wet it.
(6)壓實。
(6) Compaction.
水泥土拌和均勻后,用壓路機立即在基面上快速碾壓一遍,以暴露潛在的不平整,見圖7。然后再用平地機精平一次。每次整平都按照精平要求進行。需特別注意接縫處的整平,使接縫順適平整。
After the cement soil is mixed evenly, the road roller shall be used to quickly roll the foundation surface once to expose the potential unevenness, as shown in Figure 7. Then use the grader for fine leveling. Each leveling shall be carried out according to the requirements of fine leveling. Special attention shall be paid to the leveling of joints to make the joints smooth and flat.
好的產品成就好的服務,好的企業(yè)成就好的產品,冷再生機租賃堅持為客戶提供的服務,詳情請繼續(xù)關注我們的網站:http://www.bystreet.cn
Good products make good services, and good enterprises make good products. Cold regenerator leasing insists on providing customers with high-quality services. Please continue to pay attention to our website for details: http://www.bystreet.cn
  • 上一條:全自動粉料撒布車與冷再生機如何搭配提高質量?
  • 下一條:冷再生機水穩(wěn)層施工要注意什么?
  • 相關產品: